WE ARE UNDER CONSTRUCTION!

February 6, 2026: We have reached a major Milestone – Structural work starts on the Community Center building. 

Structural steel installation is expected to begin next week and continue over the following weeks.   This is an exciting milestone which moves the project into the start of framing and above‑grade construction.   Progress will be very visible and move fast. A few things to note:

  • All work will remain fully contained within the construction site perimeter. There will be no changes to parking lot access, Hartwell access, or any pedestrian routes.
  • Material deliveries are planned for early mornings to avoid busy hours such as daycare drop off and school traffic. We anticipate there will be 2–3 days of early deliveries for steel members and decking.
  • Delivery trucks will be escorted by crew members when exiting the site to ensure safety and smooth traffic movement.